As the metro service to Hinjewadi is scheduled to begin on Wednesday, the Pune district administration is focusing on improving access to stations and speeding up road projects in the Hinjewadi-Maan-Marunji region.
At a review meeting on Monday, District Collector Jitendra Dudi asked officials to accelerate land acquisition for six planned development-plan roads and complete the transferable development rights (TDR) process within a month. Road works are expected to start by December 2026.
The meeting, held at Dudi’s office, covered traffic congestion, road conditions, water and electricity supply, and civic services. Officials also considered ways to make metro stations more accessible to industrial-zone employees and residents of Baner, Balewadi, and Hinjewadi Phases 2 and 3.
To move the six road projects forward, Dudi directed officials to obtain consent letters from landowners. Farmers have already agreed to provide land for two roads through the floor space index (FSI) mechanism; these projects are to be prioritised. Officials were asked to meet landowners individually to seek consent for the other four roads.
The chief engineer and the relevant land acquisition officer must complete the TDR process within a month and draw up a time-bound plan for acquiring the land. They are also to present a schedule for starting construction at the next review meeting.
Dudi instructed officials to repair potholes on major roads in Hinjewadi and fix damaged road shoulders within a set period. He also called for the removal of encroachments, controls on heavy-vehicle movement, and improved coordination among agencies responsible for maintaining roads.
Officials from the Pune Metropolitan Region Development Authority (PMRDA), Maharashtra Industrial Development Corporation (MIDC), Public Works Department (PWD), police, Pimpri Chinchwad Municipal Corporation (PCMC), and other departments attended the meeting.
To address rising power demand, Dudi asked officials to begin the administrative process for transferring six acres of land to the Maharashtra State Electricity Transmission Company Limited (MSETCL). The land is intended for an electrical substation to meet both current and future needs.
With the area’s population and industrial activity growing, the Maharashtra Jeevan Pradhikaran was asked to prepare a detailed presentation on a proposed two-TMC water supply plan. It should outline present supply levels, available resources, and projected demand.
PCMC was directed to make agreements with nearby gram panchayats to collect and dispose of village waste in line with regulations. Dudi also ordered a survey of unauthorised dumping locations, followed by notices to those responsible and appropriate penalties.
All departments must submit updated progress reports at the next review. The reports are to cover road repairs and land acquisition, power infrastructure, utility relocation, sports facilities, the proposed water plan, and solid waste management, including plans for waste-processing plants.
Officials were also asked to report on traffic-management measures, the deployment of security personnel, and plans to expand bus services.